The compressor stations in Kipoi Evros Greece and in Fier Albania will be used to transport 10 bcm of natural gas per year along the entire pipeline route from east to west.
Since, July of 2017 DELTA MARITIME has been heavily involved in the Project, offering Project Logistics Services of various Oversized as well as Normal Cargo for account of Siemens SA.
To date, notable work handled by Delta on the project has included :
3 x Siemens Gas turbines (each at 36tns / 7.80 x 3.05 x 4.15m)
3 x Siemens Turbo compressors (each at 26.7tns / 6.20 x 3.68 x 3.94m)
3 x Siemens Oil cooling units (at 10.7tns / 6.35 x 2.50 x 3.99m each)
500 ton of accessories of Gas turbines & Compressors
55 x standard transports ex UK, Netherlands to the site
DELTA MARITIME scope
-Port Logistics in Piraeus
-Crane services in Piraeus for reloading of cargo on trucks
-Special transport services with Low-bed trailers
-Long term Crane services & Manpower for discharging all SIEMENS cargo from trucks at sites storage area
-Custom formalities
The project is being executed under a strict Delivery Schedule & in compliance with the highest standards of TAP/SIEMENS/DELTA QHSE requirements.